Sidewalk Installation 15th st East Bradenton

SIDEWALK INSTILLATION TO BEGIN THE WEEK OF SEPTEMBER 14th

Beginning September 2020, crews from American Design Engineering Construction, Inc. will begin installing a new section of
sidewalk along the east side of 15th Street East from 17th Avenue East to 14th Avenue East. Sidewalk construction and replacement
of the adjacent driveways is anticipated to last about 4 months and should be completed by early 2021 (weather permitting).
There will not be a need to close or detour traffic, however residents in the impacted area (See below map) along the east-side of
15th Street East should expect ongoing construction work and noise for the duration of the project. Contractor crews will be
excavating sod and dirt in order to clear a path for the new sidewalk, as well as pouring concrete during this period. Please note
that access to all driveways along the route will remain open during sidewalk installation

FAST FACTS:
• Approximate Project Cost: $133,000
• Project Funding Source: Community
Development Block Grant
• Construction Start: Mid-September 2020

 

PROJECT MANAGER:
Albert Rosenstein, P.E.
Manatee County Public Works
(941) 708-7450 Ext. 7219
albert.rosenstein@mymanatee.org

QUESTIONS? CONTACT:
Ogden Clark
Manatee County Public Works
(941) 708-7450 Ext. 7432
ogden.clark@mymanatee.org

 

 

Updated 8/27/2020 3:33 PM